1. Get at least 3 quotation from different suppliers/contractor and submit to QS. Before that every contractor must aware that what works and scope they will do. For a better to both party client must give them a clear requirement or scopes for them to submit a clear and better quotation.
2. Inden issued to contractor – Contractor to sign acceptance of Inden and start works within 14 days from the date of Indent. Contractor need to submit work programme, method statement and drawing.
3. Upon completion of works contractor to inform JKR for Join Inspection and approval for completion of works. Contractor to prepare Joint Measurement Shet.
- Contractor to sign part A and C
- JKR to sign part B
4. Complete document such as Joint Mesurement Sheet, Method Statement, Work programme, drawing and Photo send to client .
- Approval from PB and WPP at Remark part.
5. Complete document send to QS for payment process.
Note : All the information is only from my understanding. For more info and true process please refer to the right agency.