1. Get at least 3 quotation from different suppliers/contractor and submit to QS. Before that every contractor must aware that what works and scope they will do. For a better to both party client must give them a clear requirement or scopes for them to submit a clear and better quotation.
2. Inden issued to contractor – Contractor to sign acceptance of Inden and start works within 14 days from the date of Indent. Contractor need to submit work programme, method statement and drawing.
3. Upon completion of works contractor to inform JKR for Join Inspection and approval for completion of works. Contractor to prepare Joint Measurement Shet.
- Contractor to sign part A and C
- JKR to sign part B
4. Complete document such as Joint Mesurement Sheet, Method Statement, Work programme, drawing and Photo send to client .
- Approval from PB and WPP at Remark part.
5. Complete document send to QS for payment process.
Note : All the information is only from my understanding. For more info and true process please refer to the right agency.
LAWATAN KE BUKIT ANTARABANGSA DAN N.SEMBILAN - 2 - 4 NOV 2010
1. Bukit Antarabangsa
Melawat kerja-kerja pembaikan slope yang runtuh. Di mana runtuhan slope di Bukit Antarabangsa yang telah menggemparkan negara Malaysia suatu ketika dahulu yang menyebabkan 14 orang kehilangan nyawa, kerosakan harta benda , rumah berganjak dari keudukan asal dan terputus hubungan darat buat seketika.
Banyak kaedah-kaedah yang berkaitan geoteknikal work diaplikasikan di projek ini, di antaranya guniting, soil nailing, cassion pile, borepile, instrumentation dll. Yang menarik di sini ialah penggunaan cassion pile sedalam -+30m di bahagian tengah dan toe cerun. Cassion pile bertindak sebagai tembok penahan di bahagain bawah tanah. Cassion pile dilakukan secara manual.
2. Seremban Middle Ring Road
Di sini juga dapat dilihat cassion pile digunakan bagi menggantikan borepile.
3. Politeknik Nilai
Di sini mula terfikit nak beli rumah kawasan Bandar Estek untuk buat sewa kat pelajar Politeknik.
Tapi sebelum tu aku nak cerita sikit pasal nak jaga projek ni. Perkara asas yang perlu tahu untuk pantau projek ialah Time, Kualiti dan Kos.
Time
- Pantau kemajuan projek melalui CPM iaitu S curve fizikal, Task, Milestone iaitu tarikh siap.
- Program mingguan dari pihak kontraktor kena ada dan satu lagi pasal skala. Yang ni pun salah satu tool nak pantau projek.
Kualiti
Yang di pantau adalah berdasarkan ISO9000 for kualiti dan prosedur kerja, ISO 140000 for environment dan ISO 18000 untuk safety
Perkara yang dipantau ialah bahan binaan, rekod kualiti, kualiti kerja.
Kos
Monitor melalui S curve financial
Melawat kerja-kerja pembaikan slope yang runtuh. Di mana runtuhan slope di Bukit Antarabangsa yang telah menggemparkan negara Malaysia suatu ketika dahulu yang menyebabkan 14 orang kehilangan nyawa, kerosakan harta benda , rumah berganjak dari keudukan asal dan terputus hubungan darat buat seketika.
Banyak kaedah-kaedah yang berkaitan geoteknikal work diaplikasikan di projek ini, di antaranya guniting, soil nailing, cassion pile, borepile, instrumentation dll. Yang menarik di sini ialah penggunaan cassion pile sedalam -+30m di bahagian tengah dan toe cerun. Cassion pile bertindak sebagai tembok penahan di bahagain bawah tanah. Cassion pile dilakukan secara manual.
2. Seremban Middle Ring Road
Di sini juga dapat dilihat cassion pile digunakan bagi menggantikan borepile.
3. Politeknik Nilai
Di sini mula terfikit nak beli rumah kawasan Bandar Estek untuk buat sewa kat pelajar Politeknik.
Tapi sebelum tu aku nak cerita sikit pasal nak jaga projek ni. Perkara asas yang perlu tahu untuk pantau projek ialah Time, Kualiti dan Kos.
Time
- Pantau kemajuan projek melalui CPM iaitu S curve fizikal, Task, Milestone iaitu tarikh siap.
- Program mingguan dari pihak kontraktor kena ada dan satu lagi pasal skala. Yang ni pun salah satu tool nak pantau projek.
Kualiti
Yang di pantau adalah berdasarkan ISO9000 for kualiti dan prosedur kerja, ISO 140000 for environment dan ISO 18000 untuk safety
Perkara yang dipantau ialah bahan binaan, rekod kualiti, kualiti kerja.
Kos
Monitor melalui S curve financial
Subscribe to:
Posts (Atom)