Nak merapu sikit pasal benda yang nak dibuat apabila projek bermula. Macam-macam nak buat ni..........(LA dah keluar).
Sebelum tu kena tau Surat Setuju Terima, Surat Perwakilan Kuasa, Harta Pelanggan (KKR pelanggan)-kena buat verikasi harga pelanggan (borang SPK), Calibration, Mock Up,
Sediakan Q Plan - benda ni buat masa peringkat perancangan projek, iaitu sebelum proses tender dimulakan. Berkait rapat dengan D Plan. Q Plan kena sahkan dulu .....sebelum perkara-perkara berkaitan perolehan boleh di update (QS punya part).
C Plan - Disediakan pada peringkat pembinaan. Dalam ni ada macam2 antaranya jkr and kontraktor organisation chart, method statement, plan kualiti pembinaan, tanggungjawap kontraktor, ujian (benda ni kena guna spk punya senarai semak ikut skop kerja), CPM, dan sebagainya......boleh refer kat SPK.
EMP - kena prepare by EO.ISO 14000
Safety and health report, traffic report, kualiti report, progress report, environmental report.
Mesyuarat Pra Pembinaan - kena buat sebelum tarikh milik tapak. Sediakan slide pesentation. Yang hadir termasuklah jabatan2 kerajaan yang terlibat secara langsung seperti Pejabat Tanah, KKR, JAS, JPS dan lain2.
CPM - kontraktor (Planner) kena bentangkan masa pra pembinaan dan perlu di sahkan. Planner full time kat tapak) Quality Assurance Plan - Kontraktor kena prepare benda ni......ada dalam BQ.
Go trough item preliminaries dalam BQ follow up benda2 yang kontraktor kena provide..opis, staff , kenderaan dsb. Kena buat inventory senarai penerimaan barang. Dan memo serahan kepada berkenaan.
5 staff utama (PM, EO, SO, QAQC, Planner) kontraktor kena bagi CV dan requirement kena iku spec.
Site Dairy - kena isi tiap2 hari (resources and activity)
Bukak File
Survey - Kontraktor kena dapatkan TBM , nak dapat TBM kena fly dari batu sempadan. ROW data kena bagi information kat kontraktor. Benda ni daripada plan pengambilan balik tanah ada tunjuk bearing dia. Semua data ni perlu disahkan oleh licence surveyor. Kena buat Joint Pre-Com Survey., to get existing ground level (biasa buat lepas stripping top soil). Kontraktor kena submit mass haul diagram. Kalau projek retender..semua data survey perlu semak dengan alignment and existing structure kat site.
Safety and health report, traffic report, kualiti report, progress report, environmental report, project status report.
PRE COM LEVEL
Dicadangkan pre-com level di ambil selepas kerja-kerja stripping top soil siap dilakukan. Ini bagi mengelakkan berlakunya percanggahan dalam pengiraan kuantititi cut and fill pada masa akan datang.
ROAD LINE MARKING

Nak cerita sikit pasal Road Line Marking. Bila nak start buat RLM ni pastikan kita check construction drawing tu betul-betul. Terutamanya saiz dan jenis RLM serta dimension bagi setiap lorong. Pastikan betul-betul di mana kedukan RLM tersebut. Contohnya ialah di mana ukuran lebar jalan yang kita nak ambil sama daripada tepi RLM atau tengah2 RLM. Bukan apa ...kalau tak semak betul-betul nanti kita akan dapati apasal lorong jalan aku ni nampak sempit pula.....
USM - Unsuitable Material
USM .....what do you know about USM. USM is unwanted material at site. Its part of geotechnical scope. Normally the USM will be removed from site to the contractor own dumping area. And its depend to how severe and the depth of USM. The depth of USM and type of treatment has been stated in Construction Drawing. Some of the treatments are :
a. Remove and replace with sand and after that continue with normal filling. Normally for depth around 1.5m to 2m. To know the depth of USM do a MP test until 40 blows 3 consecetive . Do Atterberg Limit Test to get a LL, PL to confirm the material weather USM or not eventhough drawing has stated.
b. Remove and Replace with sand sometime install PVD and after that install with instrumentation such as pneumatic piezometer, settlement gauge, inclinometer and continue filling. Reading will be taken every 300mm of filling. And some cases it will be rest for 7 days before continue with next filling. After complete a filling add 1.5m surcharge and monitor settlement for six month.
c. Dynamic Replacement
a. Remove and replace with sand and after that continue with normal filling. Normally for depth around 1.5m to 2m. To know the depth of USM do a MP test until 40 blows 3 consecetive . Do Atterberg Limit Test to get a LL, PL to confirm the material weather USM or not eventhough drawing has stated.
b. Remove and Replace with sand sometime install PVD and after that install with instrumentation such as pneumatic piezometer, settlement gauge, inclinometer and continue filling. Reading will be taken every 300mm of filling. And some cases it will be rest for 7 days before continue with next filling. After complete a filling add 1.5m surcharge and monitor settlement for six month.
c. Dynamic Replacement
TANAH HITAM
Nak bincang sikit pasal tanah hitam kat tapak.
Macama mana nak tahu dekat kawasan kita nak bina tu ada tanah hitam atau tidak (soalan ni masa belum buat apa2 lg ....kawasan tu masih hutan lagi). Untuk makluman tanah hitam ni kalau kena air ia akan jadi macam bubur. Soalan ni aku tanya sebab ada orang bertanya kenapa you tak detect tanah hitam ni masa u buat SI dulu.
Jawapannya ialah : Ia bergantung kepada jenis SI yang kita buat....kalau kita guna boring dah tentu kita tak akan dapat sample tanah hitam ni, sebabnya ia akan jadi cair. Ia kan keluar ikut air yang di gunakan semasa kerja boring dilakukan lainlah kalau kita guna Auger. Sample tanah hitam boleh diambil guna kaedah Auger ni.
SI juga boleh dilkukan pada setiap 500m interval di bahagian tengah alignment jalan, bagi memastikan data-data SI betul-betul mewakili maklumat di tapak.
Macama mana nak tahu dekat kawasan kita nak bina tu ada tanah hitam atau tidak (soalan ni masa belum buat apa2 lg ....kawasan tu masih hutan lagi). Untuk makluman tanah hitam ni kalau kena air ia akan jadi macam bubur. Soalan ni aku tanya sebab ada orang bertanya kenapa you tak detect tanah hitam ni masa u buat SI dulu.
Jawapannya ialah : Ia bergantung kepada jenis SI yang kita buat....kalau kita guna boring dah tentu kita tak akan dapat sample tanah hitam ni, sebabnya ia akan jadi cair. Ia kan keluar ikut air yang di gunakan semasa kerja boring dilakukan lainlah kalau kita guna Auger. Sample tanah hitam boleh diambil guna kaedah Auger ni.
SI juga boleh dilkukan pada setiap 500m interval di bahagian tengah alignment jalan, bagi memastikan data-data SI betul-betul mewakili maklumat di tapak.
SOIL INVESTIGATION
Dalam membicarakan perkara ini amatlah penting bagi kita untuk mengetahui kedudukan sebenar lokasi sebenar SI dilakukan sebelum ini dan maklumat SI berikut sebelum kita melakukan kerja-kerja pembinaan. Contohnya ialah maklumat BH - type of soil, in what depth, N value dsbnya. MP - N value and at what depth. Anda boleh summarry kan maklumat tersebut yang diperolehi daripada construction drawing. Dengan maklumat yang ada dapatlah kita mengawasi tapak dengan jaya nya , especially untuk kerja-kerja Geotechinical seperti ground treatment, kerja jambatan dsbnya.